Water is Power
A Wisconsin Energy Company
Serving Since 1892

Home Contact Info Feedback Submit a Reading

 

 

 




The last time the canal was drained "1929"The Canal

Excavation of the canal began in September 1898 and was completed in June 1902. The length of the canal from the headgates (intake) to the power house is approximately 11,850 feet (2 1/4 miles). The canal varies in width from 200 to 220 feet at water level and is approximately 24 feet in depth. The water velocity varies in speed for assorted reasons. At times the water does move at speeds up to 7 mph. The entrance to the canal, which is located at the eastern end of Ashmun Bay, is controlled by four steel headgates. The upper quarter of the canal was excavated in rock, with the balance of the canal dug into the earth with timber lining. The canal is designed to use 30,000 cubic feet of water per second. 

Opening day celebration. Over 5000 in attendanceThe Powerhouse

The construction of the Edison Sault Electric Hydroelectric Plant, a historic landmark in Sault Ste. Marie, began in March 1900 and was completed in 1902. Official opening of the plant was held on October 25, 1902. At the time of completion, the plant was second only to Niagara Falls in terms of hydro development. The facility is constructed of stone and steel. Much of the stone that was used was excavated from the power canal during its construction. Additional stone was used on other local landmarks scattered throughout the City of Sault Ste. Marie.

The powerhouse is 1,340 feet long (1/4 mile) and 80 feet wide. There are 74 horizontal turbines located on the generation floor. Of the 74 turbines, 41 were installed in 1902 and the other 33 were installed in 1915-16. Each turbine has four runners, or blades, which drive the 60-cycle generators that produce the power that is eventually used in homes and businesses throughout Michigan's Eastern Upper Peninsula.

Under the most favorable operating conditions, the net plant capability is about 36,000 kilowatts. The plant power output is dependent upon the volume of water that is available through the power canal and the plant operating head. Plant operating head is the difference in water levels at the plant's forebay (south side) and the tailrace on the St. Marys River side of the facility. The average effective head at the plant is about 18.4 feet and is equivalent to the drop in elevation between Lake Superior and the lower Great Lakes.

At peak operation, the plant discharges approximately 30,000 cubic feet of water per second, which is equivalent to about 13 ½ million gallons per minute.

The head gates at Ashmun Bay The intake side of the hydro plant Original water turbines that are still in use today. Original generators

How it Works

By definition, hydroelectric means the generating of electricity by conversion of the energy of running water.

The water, which flows down the power canal, drops through the openings in the turbines to make them spin similar to a child's pinwheel in the wind. The turbine turns the rotor, which is the last moving part in the sequence of events. Its turning causes electricity to flow out of the wires in the stator.

It is a fact that when a magnet is moved in the vicinity of a wire (typically copper), electricity flows along the wire. When the magnet moves, the "lines of force" that surround the magnet cut across the wire, inducing a flow of free electrons in the wire. Flowing electrons are electricity.

Hydro plant main board in use until 1992.Modern Operations

Edison Sault Electric Company purchased the hydro plant and canal in 1963 from the Union Carbide Company for $1.5 million. An additional $1.0 million was spent to convert the plant from 25-cycle electricity to 60-cycle electricity. In 1992, the Company completed an $8.0 million modernization and automation project in the plant which enhanced the safety and efficiency of the plant for years to come.

Over the last five years, Edison Sault Electric has been allocated, on average, 17,400 cubic feet per second to operate the hydro plant. This allowed the plant to operate at approximately 58% of its designed capacity. Total plant generation accounted for approximately 1/5 of the total power requirements for the combined Edison Sault and Cloverland Electric systems. Edison Sault has a contract in place with the Secretary of the Army at least until the year 2025, and possibly as long as the year 2040, for use of the water that runs through the plant. The plant may very well be expected to be operational until then.

 

 

 

To contact Customer Service, send mail to customerserv@edisonsault.com.
Send mail to information@edisonsault.com with questions or comments about this web site.
Last modified: March 16, 2005
Water is Power
Site hosted by
Serving Since 1892