Mackinac
Island Outage Report
Summary of Staffing, Decisions and
Logistical Issues |

|

| Date |
Employees/Contract Personnel on Site |
ESE Management Persons on Site |
Significant Decisions |
Significant Logistical Issues |
| Sat, 7/22 |
ESE - 1 Mgt, 5 BU |
Davidson |
Connect spare cable & locate & repair problem. |
|
| |
|
|
|
|
| Sun, 7/23 |
ESE - 2 Mgt, 8 BU |
Davidson, Litzner |
Go to one circuit only and locate, repair problem
Sawruk, Maas, Litzner notified, Litzner on site. |
Two more cable failures occur later in day. |
| |
|
|
|
|
| Mon, 7/24 |
ESE - 3 Mgt, 8 BU
4 DTE, CPCO |
Davidson, Litzner
Maas |
Location, splicing ongoing. Call to Kerite;
calls to WE, CPCO, DTE. |
Two more cable failures occur later in day. |
| |
|
|
|
|
| Tues, 7/25 |
ESE - 3 Mgt, 8 BU
6 DTE, CPCO |
Davidson, Litzner
Maas |
Location, splicing ongoing. |
|
| |
|
|
|
|
| Wed, 7/26 |
ESE - 3 Mgt, 8 BU
5 DTE, WE, Kerite |
Davidson, Lit.zner
Mass |
Location, splicing ongoing. Mackinac Island City
asks for diesels to be brought in. |
Demobilization of diesels begins in Coldwater Michigan.
Mobilization of transformers recd from Pennsylvania. |
| |
|
|
|
|
| Thurs, 7/27 |
ESE - 4 Mgt, 8 BU
5 DTE, WE, Kerite |
Davidson, Litzner
Maas, Deverna |
Location, splicing ongoing, |
Mobilization of Durocher barge for diesels, transformers
Mobilization of diesel supply. |
| |
|
|
|
|
| Fri. 7/28 |
ESE - 8 Mgt, 12 BU
20 DTE, WE, Kerite, others |
Davidson, Litzner
Maas, Deverna |
Construction of diesel interfaces to system.
Substation changes to accept diesels. |
Diesels and transformer arrive, expedite parts begins |
| |
|
|
|
|
| Sat, 7/29 |
ESE - 10 Mgt, 14 BU
10 DTE, WE, Kerite, others |
Davidson, Litzner
Maas, Deverna, Weber |
Construction of new onshore facilities on Mackinac Island. |
Diesels online. Expedite new 350 cable, expedite parts. |
| |
|
|
|
|
| Sun, 7/30 |
ESE - 10 Mgt, 14 BU
10 DTE, WE, Kerite, others |
Davidson, Litzner
Maas, Deverna, Weber |
Construction of new onshore facilities on St Ignace. Expedite new 350 cable, expedite parts. |
|
| |
|
|
|
|
| Mon, 7/31 |
ESE -10 Mgt, 14 BU
8 DTE, Kerite, others |
Davidson, Litzner
Maas, Deverna |
Construction of new facilities continues.
Splicing for new facilities. |
|
| |
|
|
|
|
| Tues, 8/1 |
ESE - 10 Mgt, 14 BU
7 DTE, WE, Kerite, others |
Davidson, Litzner
Mass, Deverna |
Splicing for new facilities. System testing for all
new and existing system. |
|
| |
|
|
|
|
| Wed, 8/2 |
ESE - 5 Mgt, 8 BU |
Davidson, Litzner |
System switched back to submarine cables. |
Diesels go offline. |